| | Link to the record of the data center this timeline corresponds to. | | 100%
403 out of 403 records |
| | As-of date for the status/metrics. | | 100%
403 out of 403 records |
| | Short description of the construction status at that point in time. | Building 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according to a regulatory filing. Building 5 still has light construction activity, while Building 6 still lacks chillers. The on-site power plant to the right of Building 2 looks complete. | 100%
403 out of 403 records |
| | Count of buildings operational by this date. | | 100%
402 out of 403 records |
| | Total IT power capacity in megawatts, including power for GPU servers, network infrastructure and storage. | | 100%
403 out of 403 records |
| | Total facility power capacity in megawatts, including the IT power and power for cooling, lighting, etc. | | 100%
403 out of 403 records |
| | The number of NVIDIA H100 GPUs that are equivalent to this data center’s compute capacity, based on 8-bit OP/s. | | 100%
402 out of 403 records |
| | Maximum compute capacity in any format 8 bits or wider. Estimates usually based on best guesses of what chips would be used at the location and the power estimate to infer the number of these chips. | | 100%
402 out of 403 records |
Total capital cost (2025 USD billions) | | Total capital cost of the entire facility by this date, including IT hardware (such as GPUs), mechanical and electrical equipment, building shell and white space, construction labor, land acquisition, etc. | | 100%
403 out of 403 records |
Compute cost (2025 USD billions) | | Total capital cost of the IT hardware in the data center buildings. Includes GPUs, networking, server racks, etc. | | 100%
403 out of 403 records |
Construction cost (2025 USD billions) | | Total of all capital costs other than compute, including building shell and white space, mechanical and electrical, HVAC systems, construction labor, land acquisition, etc. | | 100%
403 out of 403 records |
Annual operating cost (2025 USD billions) | | Annual total of all operating costs, including energy consumption, taxes, maintenance, labor, and water. | | 100%
403 out of 403 records |
| | Estimated average water consumed by the data center in million gallons/day. | | 12%
49 out of 403 records |
| | Lookup to the current number of H100 equivalents for the data center as of today. Used to group and sort the table. | | 100%
403 out of 403 records |