QTS Cedar Rapids

Cedar Rapids, Iowa, United States

QTS Cedar Rapids is an AI data center under construction with AI chips owned by . In Q4 2027, we project it to host an estimated 3,669k H100-equivalents of compute, supported by 1,133 MW of IT power at a capital cost of $42.9 B.

The timeline of IT power and compute capacity is based on satellite imagery, our cooling equipment power model, chip availability, and grid operator data.

The estimated Phase 1 power matches a 616 MW load request filed by a QTS shell company, though the full two-phase plan would need more than double that.

STATUSUnder construction
Show compute as
Satellite view of QTS Cedar Rapids

Satellite imagery

Latest: May 5, 2026 · 3 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

0H100-eq

08-bit OP/s

PROJECTED

3,669kH100-eq

7.26e218-bit OP/s

CURRENT IT POWER

0MW

PROJECTED IT POWER

1,133MW

CURRENT COST

$0.0B

PROJECTED COST

$42.9B

Buildout

Jan 17, 20250K H100e
Jan 17, 2025

Land clearing begins for Building 1-3.

Oct 27, 2025

Building 1 roof complete, with air-cooled chillers in place. Building 2 and 3 roofs are partly completed. Building 4 and 5 have a foundation.

Apr 16, 2026

Based on satellite imagery, the Buildings 1-3 shells look complete. Buildings 4-6 are far along, with roofs largely in place, while the eastern Building 7 foundation is well underway. No buildings operational yet.

May 7, 2026

Similar to April, Buildings 1-3 shells look complete. Buildings 4-6 are still far along, and the eastern Building 7 foundation is still underway.

Nov 15, 2026

Buildings 1-3 are operational. Based on the expected completion date reported by local news: “A QTS spokesperson said in July [2025] that the first phase of the project was expected to be completed in late 2026."

Compute
1,137kH100-eq
IT Power
448MW
Cost
$17.0B
Nov 15, 2027

Buildings 4-7 are operational. Based on the expected completion date reported by local news: “A QTS spokesperson said in July [2025] that [...] The second phase is expected to be completed in late 2027."

Compute
3,669kH100-eq
IT Power
1,133MW
Cost
$42.9B

Sources

  1. MISO new load announcements
  2. Article by The Gazette
  3. Article by Corridor Business Journal
  4. Post by GLD Commercial