Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared. The many cars and trucks parked beside the buildings suggest commissioning is still underway, so we’re not counting any buildings operational yet. Buildings 4-6 shells appear complete, and Building 7 is nearly 90% roofed. This is based on high-resolution satellite imagery from this date.