QTS Cedar RapidsCedar Rapids, Iowa, United States
CHIP OWNERMeta
USERMeta
Full details →

CONSTRUCTION STATUS
Oct 23, 2026

Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared. The many cars and trucks parked beside the buildings suggest commissioning is still underway, so we’re not counting any buildings operational yet. Buildings 4-6 shells appear complete, and Building 7 is nearly 90% roofed. This is based on high-resolution satellite imagery from this date.

Compute
0H100e
IT Power
0MW
Cost
$0.0B
Building
Substation
On-site power
Backup power
Cooling