QTS Cedar RapidsCedar Rapids, Iowa, United States
Full details →

CONSTRUCTION STATUS
May 7, 2026

Similar to April, Buildings 1-3 shells look complete. Buildings 4-6 are still far along, and the eastern Building 7 foundation is still underway.

Compute
0H100-eq
IT Power
0MW
Cost
$0.0B
Building
Substation
On-site power
Backup power
Cooling