Back to Directory
Updated Nov. 6, 2026

Huawei Horinger

Hohhot, Inner Mongolia, China

Huawei Horinger is an operational AI data center with AI chips owned by Huawei. It hosts an estimated 81k H100-equivalents of AI compute, supported by 170 MW of IT power at a capital cost of $6.4 B. In Q1 2028, we project it to rise to 141k H100e AI compute, 351 MW IT power and a cost of $13.3 B. We estimate that it uses Huawei Ascend 910C and Huawei Ascend 910B chips.

The timeline of IT power and AI compute capacity is based on satellite imagery, our cooling equipment power model, company disclosures, chip availability, and chip efficiency.

One report suggests the Horinger campus could eventually grow to as many as 50 buildings under an unconfirmed Phase 2.

CHIP OWNERHuaweiSTATUSOperational
Show compute as
Satellite view of Huawei Horinger

Satellite imagery

Latest: Aug. 20, 2026 · 7 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

81kH100e

1.60e208-bit OP/s

PROJECTED

141kH100e

2.79e208-bit OP/s

CURRENT IT POWER

170MW

PROJECTED IT POWER

351MW

CURRENT COST

$6.4B

PROJECTED COST

$13.3B

Buildout

Oct 8, 20230K H100e
Oct 8, 2023

Land clearing begins simultaneously for all three zones (West, North, and South) after an official ceremony. The West and South zones later have the cooling capacity indicative of AI workloads, while the North Zone does not.

Feb 24, 2025

In the West Zone, Building 1 is structurally complete. In the South Zone, Building 4 is structurally complete except for several cooling towers to be installed later. Buildings 2 (West Zone) and 5 (South Zone) have shells under construction.

Jun 8, 2025

In the South Zone, paving and landscaping around Building 4 is mostly complete, while Building 5 still needs cooling and backup generators to be installed.

Jun 11, 2025

In the West Zone, Building 1 is operational, based on its structural completion and colored motion artifacts on some of the cooling tower fans.

Compute
19kH100e
IT Power
42MW
Cost
$1.6B
Mar 5, 2026

Building 1 appears to have condensed water vapor above some cooling towers, suggesting they are still operating. Cooling towers have been added to Building 4, but we do not see any condensed water vapor, and there is still a crane over the building. So we don't think Building 4 is operational at full capacity yet.

Compute
19kH100e
IT Power
42MW
Cost
$1.6B
May 12, 2026

Building 4 is operational, based on its structural completion, the colored motion artifacts on some of the cooling tower fans, and cars parked out front (between the main building and the backup generator enclosure). Building 5 is almost structurally complete, but there is still some work to do in front of the backup generator enclosure.

Compute
41kH100e
IT Power
87MW
Cost
$3.3B
Jun 7, 2026

In the West Zone, Building 2 is structurally complete but still has some construction equipment around it.

Compute
41kH100e
IT Power
87MW
Cost
$3.3B
Aug 18, 2026

In the South Zone, Building 5 is operational, based on its structural completion, and the colored motion artifacts on the some of the cooling tower fans. Building 6 (South Zone) is under construction. In the West Zone, Building 3 has not begun construction.

Compute
81kH100e
IT Power
170MW
Cost
$6.4B
Dec 22, 2026

In the West Zone, Building 2 is operational (estimate). A local government announcement said a "completion acceptance filing" was completed for Building 2 around September 23, 2026, "marking a critical step toward the project's entry into operation". We assume this corresponds to structural completion, since there was minimal construction activity by August 18th. We then allow 3 more months for a full fit-out of AI servers.

Compute
104kH100e
IT Power
216MW
Cost
$8.2B
Feb 17, 2028

Building 6 (South Zone) is operational (estimate). This was the only new building under construction as of August 2026. We estimate the operational date based on an average of (1) previous buildings taking about 2 years on average from starting the building shell to becoming operational at ~full capacity, (2) a similar building at the Huawei Wuhu campus taking an estimated 550 days to become fully operational. Building 6 can reportedly support 100,000 AI accelerator cards and will deploy Huawei Ascend 950 chips. Based on the timing, we assume it has capacity for 100,000 Ascend 950DT chips (Ascend 950DT is ramping a few months later than 950PR). As with the other buildings, we multiply this capacity by the reported rack occupancy rate for the Horinger New Area (about 76%).

Compute
141kH100e
IT Power
351MW
Cost
$13.3B

Sources

View our calculations for this data center, or read more about our methodology.