Huawei HoringerHohhot, Inner Mongolia, China
CHIP OWNERHuawei
Full details →

CONSTRUCTION STATUS
Aug 18, 2026

In the South Zone, Building 5 is operational, based on its structural completion, and the colored motion artifacts on the some of the cooling tower fans. Building 6 (South Zone) is under construction. In the West Zone, Building 3 has not begun construction.

Compute
81kH100e
IT Power
170MW
Cost
$6.4B
Building
Substation
On-site power
Backup power
Cooling