New Albany, Ohio, United States
Google New Albany is an operational AI data center in New Albany, OH, USA, with AI chips owned by Google and used by Google DeepMind (likely). It hosts an estimated 207k H100-equivalent chips, scaling toward a projected 318k H100-equivalent chips — supported by 339 MW of IT power, rising to 453 MW — at a capital cost of $12.8 B, rising to $17.2 B. We estimate that it uses Google TPU v5e, Google TPU v5p, Google TPU v6e, and Google TPU v7 chips. The timeline of IT power and compute capacity is based on satellite imagery, our cooling equipment power model, chip availability, and chip efficiency.
Satellite imagery
CURRENT COMPUTE
207k H100-eq
4.10e20 8-bit OP/s
PROJECTED
318k H100-eq
6.29e20 8-bit OP/s
CURRENT IT POWER
339 MW
PROJECTED IT POWER
453 MW
CURRENT COST
$12.8 B
PROJECTED COST
$17.2 B
Building 1 is operational. Based on ~7 months since roof being completed, and cooling towers being installed sometime within that period. Building 2 roof is complete.
Building 2 is operational. Google Earth imagery shows 6 cooling towers installed as of 2024-04-20, and a final 7th unit appeared as of 2024-09-13, with minimal construction around the building. Building 3 roof is also complete.
Building 3 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 4 still has some work around the cooling towers. Work is underway on Building 5 - some walls and a few backup generators are in place.
Building 4 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 5 roof is half complete. About half of the backup generators are in place. One cooling tower is partly built.
Water vapor from cooling towers is present across Building 1-4, confirming their operation. Building 5 roof is still incomplete, but most backup generators and 5 cooling towers have been installed.
Building 5 has more cooling towers installed but not complete, and the roof is almost complete.
Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational.
Building 5 is operational. Estimated from the high-res image from May.
Read more about our methodology.