Google New AlbanyNew Albany, Ohio, United States
OWNERGoogle
USERGoogle DeepMind
Full details →

CONSTRUCTION STATUS
May 18, 2026

Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational.

Compute
207kH100-eq
IT Power
339MW
Cost
$12.8B
Building
Grid power
On-site power
Backup power
Cooling