Abilene, Texas, United States
OpenAI Stargate Shackelford is an AI data center under construction in Abilene, TX, USA, with AI chips owned by Oracle and used by OpenAI. No IT power is online yet; it is projected to host an estimated 3,623k H100-equivalent chips — supported by 1,400 MW — at a capital cost of $53.0 B. The timeline of IT power and compute capacity is based on satellite imagery, company disclosures, chip availability, and chip efficiency. Just 20 km from the original Abilene site, Shackelford is the second U.S. Stargate location, developed by Vantage under the name “Frontier.”
Satellite imagery
CURRENT COMPUTE
0 H100-eq
0 8-bit OP/s
PROJECTED
3,623k H100-eq
7.17e21 8-bit OP/s
CURRENT IT POWER
0 MW
PROJECTED IT POWER
1,400 MW
CURRENT COST
$0.0 B
PROJECTED COST
$53.0 B
Land clearing begins.
The layout of Buildings 1-5 is visible. Steel framing has just started on Building 1.
Steel framing is underway for Buildings 1-3, and roofing is underway for Building 1.
Building 1 is operational (estimate). TDLR lists the construction completion date for Building 1 as 2027-02-15. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 2 is operational (estimate). TDLR lists the construction completion date for Building 2 as 2027-04-19. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 3 is operational (estimate). TDLR lists the construction completion date for Building 3 as 2027-05-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 4 is operational (estimate). TDLR lists the construction completion date for Building 4 as 2027-08-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 5 is operational (estimate). TDLR lists the construction completion date for Building 5 as 2027-09-08. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 6 is operational (estimate). TDLR lists the construction completion date for Building 6 as 2027-10-04. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 7 is operational (estimate). TDLR lists the construction completion date for Building 7 as 2027-11-12. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 8 is operational (estimate). TDLR lists the construction completion date for Building 8 as 2028-04-17. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 9 is operational (estimate). TDLR lists the construction completion date for Building 9 as 2028-04-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 10 is operational (estimate). TDLR lists the construction completion date for Building 10 as 2028-05-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Read more about our methodology.