YTL Johor

Kulai, Johor, Malaysia

YTL Johor is an operational AI data center with an unknown owner. It hosts an estimated 154k H100-equivalents of AI compute, supported by 113 MW of IT power at a capital cost of $4.3 B. In Q3 2028, we project it to rise to 585k H100e AI compute, 284 MW IT power and a cost of $10.8 B. We estimate that it uses Nvidia B200 and Nvidia B300 chips.

The timeline of IT power and AI compute capacity is based on satellite imagery, company disclosures, our cooling equipment power model, regulatory filings, third-party reporting, and drone imagery.

STATUSOperational
Show compute as
Satellite view of YTL Johor

Satellite imagery

Latest: Jul. 13, 2026 · 1 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

154kH100e

3.04e208-bit OP/s

PROJECTED

585kH100e

1.16e218-bit OP/s

CURRENT IT POWER

113MW

PROJECTED IT POWER

284MW

CURRENT COST

$4.3B

PROJECTED COST

$10.8B

Buildout

Nov 1, 20230K H100e
Nov 1, 2023

Land clearing begins for Building 1.

Nov 3, 2025

Building 1 is operational with Nvidia GB200s, according to the local investment development authority.

Compute
24kH100e
IT Power
20MW
Cost
$0.8B
Mar 14, 2026

Building 2 is operational, assuming 3 months to structural completion plus 3 months fit-out after this video. Solar panels are also being installed to the north west of the campus.

Compute
138kH100e
IT Power
100MW
Cost
$3.8B
May 15, 2026

Building 1 added 4 two-fan cooling towers (config 3), installed mid May of 2026. This capacity is not reflected in any disclosure (the building is still reported at 20MW IT load).

Compute
154kH100e
IT Power
113MW
Cost
$4.3B
Jul 13, 2026

Satellite imagery confirms Buildings 1 and 2 are structurally complete. Buildings 3 and 4 are underway, and construction equipment can be seen on the plot for Building 5. Extensive solar panel arrays have been built out.

Compute
154kH100e
IT Power
113MW
Cost
$4.3B
Aug 1, 2028

Estimate: all five AI buildings operational. The mean time from first ground activity to operational across buildings 1 and 2 was 25.6 (25.1 and 26.0 months). Buildings 3 and 4 have been underway since Mar 2026, and building 5's plot only has construction equipment as of Jul 2026, so +25 months gives Aug 2028 as campus completion. Company guidance is faster: capacity "expected to double to 600MW by the end of 2027" per Kenanga via The Star; JDC4 phases Sep-25/Sep-26/Sep-27 per MIDF. The resulting ~429MW IT independently matches Kenanga's "expected IT load of 430MW" for the 600MW park (Kenanga, 9 Dec 2024).

Compute
585kH100e
IT Power
284MW
Cost
$10.8B

Sources

  1. Official YTL page for the campus
  2. YTL press release on the use of GB200's
  3. Aerial footage including the campus

View our calculations for this data center, or read more about our methodology.