Updated Jul. 3, 2026

OpenAI Stargate UAE

Abu Dhabi, Abu Dhabi, United Arab Emirates

OpenAI Stargate UAE is an AI data center under construction in Abu Dhabi, Abu Dhabi, UAE, with AI chips owned by G42 (likely) and used by OpenAI. No IT power is online yet; it is projected to host an estimated 2,021k H100-equivalent chips — supported by 1,000 MW — at a capital cost of $37.9 B. The timeline of IT power and compute capacity is based on satellite imagery, company disclosures, and chip availability. Stargate UAE is the first Stargate cluster outside the U.S.; reported export agreements suggest G42 and/or Oracle can acquire 100,000 state-of-the-art NVIDIA chips per year.

OWNER G42 STATUS Under construction USER OpenAI PROJECT Stargate
Show compute as
Satellite view of OpenAI Stargate UAE

Satellite imagery

Latest: Nov. 16, 2025 · 1 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

0 H100-eq

0 8-bit OP/s

PROJECTED

2,021k H100-eq

4.00e21 8-bit OP/s

CURRENT IT POWER

0 MW

PROJECTED IT POWER

1,000 MW

CURRENT COST

$0.0 B

PROJECTED COST

$37.9 B

HardwareNvidia B300, Nvidia R200

CoolingUnknown

Buildout

Jun 9, 20250
Jun 9, 2025

Land clearing begins for Building 1 and 2

Nov 16, 2025

Building 1 and 2 are partly constructed. No clear evidence of more buildings starting construction.

Dec 1, 2026

Building 1 and 2 are operational. The similar data center in Ajman, UAE was delayed by over a year, now due in December 2026 (compare 1, 2). The buildings here looked 3-6 months behind the Ajman building as of November 2025, but they were moving faster. So we think Building 1 and 2 are on track for 200 MW by December 2026, along with the Ajman building.

Compute
253kH100-eq
IT Power
200MW
Cost
$7.6B
Jan 1, 2028

1 GW of IT power is operational. We haven’t seen expansion beyond 200 MW as of November 2025. Optimistically, 8 more 100 MW buildings start construction in December 2025, in parallel, and take 1.5 years like the first two buildings, hitting 1 GW by Q3 2027. More realistically, there's some staggering of construction over several months, like Stargate Abilene. Our median estimate is January 2028.

Compute
2,021kH100-eq
IT Power
1,000MW
Cost
$37.9B

Sources

  1. News update with timelapse of construction
  2. Announcement of the (separate) 100 MW Khazna Ajman data center
  3. News about the US approval of NVIDIA chips in the UAE

Read more about our methodology.