San Antonio, Texas, United States
Microsoft SAT14 is an operational AI data center with AI chips owned by Microsoft. It hosts an estimated 45k H100-equivalents of compute, supported by 47 MW of IT power at a capital cost of $1.8 B. We estimate that it uses Nvidia H100 and Nvidia B300 chips.
The timeline of IT power and compute capacity is based on satellite imagery, our cooling equipment power model, regulatory filings, chip availability, and chip efficiency.
Satellite imagery
CURRENT COMPUTE
45k H100-eq
8.94e19 8-bit OP/s
CURRENT IT POWER
47 MW
PROJECTED IT POWER
47 MW
CURRENT COST
$1.8 B
PROJECTED COST
$1.8 B
Land clearing for the site is almost complete. Informed using imagery on Google Earth
Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the on-site substation was previously incomplete, so we believe it was only operational at this point.
Building 2 chiller installation is a little more than halfway complete, and chiller installation for the last data hall of Building 1 is also around halfway complete.
No more visible construction around either building, just a little equipment. Roads fully built around buildings as well.
Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31.