Bjerkvik, Narvik, Norway
Microsoft Narvik Norway is an AI data center under construction with AI chips likely owned by Nscale and likely used by Microsoft. In Q4 2026, we project it to host an estimated 265k H100-equivalents of compute, supported by 92 MW of IT power at a capital cost of $3.5 B.
The timeline of IT power and compute capacity is based on satellite imagery, chip efficiency, chip availability, third-party reporting, our cooling equipment power model, and company disclosures.
The data center campus will use local hydropower with electricity costs of 4 to 5 cents per unit versus up to 10 cents in other parts of Europe.

Satellite imagery
CURRENT COMPUTE
0H100-eq
08-bit OP/s
PROJECTED
265kH100-eq
5.25e208-bit OP/s
CURRENT IT POWER
0MW
PROJECTED IT POWER
92MW
CURRENT COST
$0.0B
PROJECTED COST
$3.5B
Land clearing and site prep begins at least as early as July 2023.
Site prep continues for Buildings 1, 2, and 3.
Building 1 starts to go up.
Building 1 cooling looks complete. Backup generator install continues adjacent to B1. Building 2 cooling install continues. Ground prep for generators next to B2. Cooling install appears to continue on Building 3. Construction equipment present all around site. We believe no buildings are operational at this time.
Building 1 cooling looks complete. Backup generator install continues adjacent to B1. Building 2 cooling install continues. Backup generator concrete pads are there, but no equipment install visible. Cooling install appears to continue on Building 3. Construction equipment present all around site. We believe no buildings are operational at this time.
We believe Buildings 1 and 2 will be fully operational by the end of H2 2026