Updated Jul. 15, 2026

Meta Jeffersonville

Jeffersonville, Indiana, United States

Meta Jeffersonville is an operational AI data center hosting an estimated 203k H100-equivalent chips — supported by 178 MW of IT power — at a capital cost of $6.7 B. We estimate that it uses Nvidia B300 chips. The timeline of IT power and compute capacity is based on satellite imagery, our cooling equipment power model, structural similarity to known buildings, chip availability, and chip efficiency.

OWNER Meta STATUS Operational USER Meta
Show compute as
Satellite view of Meta Jeffersonville

Satellite imagery

Latest: Mar. 12, 2026 · 1 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

203k H100-eq

4.02e20 8-bit OP/s

CURRENT IT POWER

178 MW

PROJECTED IT POWER

178 MW

CURRENT COST

$6.7 B

PROJECTED COST

$6.7 B

HardwareNvidia B300

CoolingAir-cooled chiller

Buildout

Feb 1, 20240K H100e
Feb 1, 2024

Land clearing begins.

Mar 6, 2026

Building 1 and 2 shell and cooling look complete, but there's still construction activity. We give it another 3 months to operational.

Jun 4, 2026

Building 1 and 2 are operational.

Compute
203kH100-eq
IT Power
178MW
Cost
$6.7B

Sources

  1. Official Meta Fact Sheet
  2. Turner Construction contractor presenting their involvement in the project.
  3. Air Quality Permit for initial buildout

Read more about our methodology.