Meta Cheyenne

Cheyenne, Wyoming, United States

Meta Cheyenne is an AI Data Center under construction, projected to host an estimated 251k H100-equivalent chips — supported by 220 MW — at a capital cost of $8.3 B. The timeline of IT power and compute capacity is based on satellite imagery, our cooling equipment power model, structural similarity to known buildings, chip availability, and chip efficiency. Announced in July 2024, Cheyenne will be Meta’s 21st data center in the U.S.

OWNER Meta STATUS Under construction USER Meta
Show compute as
Satellite view of Meta Cheyenne

Satellite imagery

Latest: Mar. 21, 2026 · 1 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

0 H100-eq

0 8-bit OP/s

PROJECTED

251k H100-eq

4.97e20 8-bit OP/s

CURRENT IT POWER

0 MW

PROJECTED IT POWER

220 MW

CURRENT COST

$0.0 B

PROJECTED COST

$8.3 B

HardwareNvidia B300

CoolingUnknown

Buildout

May 15, 20240K H100e
May 15, 2024

Ground is being cleared.

Jan 30, 2025

Structure for Building 1 and 2 under construction.

Mar 22, 2026

Building 1 shell and cooling looks complete, Building 2 roof almost complete.

Jul 25, 2026

Both buildings estimated to be operational.

Compute
173kH100-eq
IT Power
152MW
Cost
$5.8B
Feb 15, 2027

Buildings 3 and 4 are similar in style and size to the ones seen at the Prometheus site, we estimate their operability based on that timeline.

Compute
251kH100-eq
IT Power
220MW
Cost
$8.3B

Sources

  1. Meta Introduction to the Cheyenne Project
  2. Fortis Construction announcement
  3. Press announcement suggesting a 2027 operational date

Read more about our methodology.