Meta Bowling Green

Bowling Green, Ohio, United States

Meta Bowling Green is an AI data center under construction with AI chips owned and used by Meta. In Q1 2028, we project it to host an estimated 855k H100-equivalents of AI compute, supported by 422 MW of IT power at a capital cost of $16.0 B.

The timeline of IT power and AI compute capacity is based on satellite imagery, our cooling equipment power model, regulatory filings, structural similarity to known buildings, and chip availability.

OWNERMetaSTATUSUnder constructionUSERMeta
Show compute as
Satellite view of Meta Bowling Green

Satellite imagery

Latest: Jul. 30, 2026 · 2 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

0H100-eq

08-bit OP/s

PROJECTED

855kH100-eq

1.69e218-bit OP/s

CURRENT IT POWER

0MW

PROJECTED IT POWER

422MW

CURRENT COST

$0.0B

PROJECTED COST

$16.0B

Buildout

Nov 1, 20240K H100e
Nov 1, 2024

Land clearing begins.

Feb 14, 2026

Buildings 1 and 2 under construction. Building 1's chillers are almost all in place, while only half of Building 2's are. Optimus substation, which is the substation on site, and the expansion of Dowling Substation, an existing substation to the northeast of the data center, appear complete.

Jul 30, 2026

Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the Apollo Power Generation Project (a BTM power plant built just to the east of the data center) is in progress, with foundations poured and generation equipment being set in place.

Feb 1, 2027

Building 1 is operational, based on a 5 month extrapolation from its roof completion date.

Compute
104kH100-eq
IT Power
86MW
Cost
$3.3B
Apr 1, 2027

Building 2 is operational, based on construction progress as of Sep 2026 and foundations being laid around 2 months after Building 1.

Compute
197kH100-eq
IT Power
163MW
Cost
$6.2B
Jan 1, 2028

Buildings 3 and 4 are operational, based on their construction starting 11 months after Building 1. We assume they are powered by the 350 MW Apollo Power Generation Project.

Compute
855kH100-eq
IT Power
422MW
Cost
$16.0B

Sources

  1. Meta letter to Middleton Township
  2. Construction notice for new transmission lines to data center substation
  3. Ohio Power Siting Board announcement
  4. Apollo Power Generation Project Letter of Notice Appendix A, with a project timeline

View our calculations for this data center, or read more about our methodology.