Huawei Wuhu

Wuhu, Anhui, China

Huawei Wuhu is an operational AI data center with AI chips owned by Huawei. It hosts an estimated 53k H100-equivalents of AI compute, supported by 197 MW of IT power at a capital cost of $7.5 B. In Q4 2027, we project it to rise to 151k H100e AI compute, 453 MW IT power and a cost of $17.2 B. We estimate that it uses Huawei Ascend 910C, Nvidia H20, Huawei Ascend 910B, and Huawei Ascend 950PR chips.

The timeline of IT power and AI compute capacity is based on satellite imagery, our cooling equipment power model, regulatory filings, drone imagery, structural similarity to known buildings, third-party reporting, and chip availability.

CHIP OWNERHuaweiSTATUSOperational
Show compute as
Satellite view of Huawei Wuhu

Satellite imagery

Latest: Jul. 14, 2026 · 2 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

53kH100e

1.05e208-bit OP/s

PROJECTED

151kH100e

3.00e208-bit OP/s

CURRENT IT POWER

197MW

PROJECTED IT POWER

453MW

CURRENT COST

$7.5B

PROJECTED COST

$17.2B

Buildout

Dec 1, 20220K H100e
Dec 1, 2022

Land clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after.

Jan 1, 2025

The first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. We multiply each building's estimated capacity by an assumed 65% rack occupancy rate. This is close to the ~62–64% reported for Wuhu and other national data center hubs in 2023, and matches Anhui's 65% target for the Wuhu cluster. Occupied capacity is assumed to be all AI chips.

Compute
8kH100e
IT Power
44MW
Cost
$1.7B
Mar 1, 2025

Three buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but as of 2026 does not have the cooling sufficient for AI. Assumes a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.

Compute
20kH100e
IT Power
118MW
Cost
$4.5B
Nov 1, 2025

Four buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.

Compute
36kH100e
IT Power
156MW
Cost
$5.9B
Jan 24, 2026

Four buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have sufficient cooling for AI despite its backup generators. The remaining three buildings, one per campus, have not begun construction.

Compute
36kH100e
IT Power
156MW
Cost
$5.9B
Jun 1, 2026

Four buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining.

Compute
36kH100e
IT Power
156MW
Cost
$5.9B
Aug 6, 2026

On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in approximately one month, given that it is structurally complete and 75% of its cooling looks to be installed. On the east campus, building 9 is under construction.

Compute
36kH100e
IT Power
156MW
Cost
$5.9B
Nov 1, 2026

Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.

Compute
53kH100e
IT Power
197MW
Cost
$7.5B
Dec 31, 2026

Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is about 3.7x more power than one of the previous buildings, based on the size and quantity of cooling and backup generator equipment observed in satellite imagery. As with the other buildings, we assume 65% rack occupancy.

Compute
119kH100e
IT Power
360MW
Cost
$13.6B
Dec 1, 2027

All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is excluded due to insufficient cooling. The time from observed land-clearing to operational is 23-26 months based on previous buildings. As with the other buildings, we assume 65% rack occupancy.

Compute
151kH100e
IT Power
453MW
Cost
$17.2B

Sources

View our calculations for this data center, or read more about our methodology.