Back to Directory
Updated Sep. 11, 2026

Google Fort Wayne

Fort Wayne, Indiana, United States

Google Fort Wayne is an AI data center under construction with AI chips owned by Google and possibly used by Google DeepMind. In Q2 2028, we project it to host an estimated 2,941k H100-equivalents of compute, supported by 863 MW of IT power at a capital cost of $32.7 B.

The timeline of IT power and compute capacity is based on satellite imagery, our cooling equipment power model, chip availability, and chip efficiency.

Fort Wayne is one of the first sites to use Google’s new, larger data center design with expanded cooling, and is projected to draw roughly 1 GW of total facility power when completed in 2028.

OWNERGoogleSTATUSUnder constructionUSERGoogle DeepMind (speculative)
Show compute as
Satellite view of Google Fort Wayne

Satellite imagery

Latest: Aug. 19, 2026 · 2 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

0H100-eq

08-bit OP/s

PROJECTED

2,941kH100-eq

5.82e218-bit OP/s

CURRENT IT POWER

0MW

PROJECTED IT POWER

863MW

CURRENT COST

$0.0B

PROJECTED COST

$32.7B

HardwareUnknown

Buildout

Apr 1, 20240K H100e
Apr 1, 2024

First signs of development/land clearing

Sep 13, 2024

Roof complete on Building 1 (the 'H'), although we suspect this building is not for AI compute due to the construction speed, irregular design, and lack of external cooling.

Jun 10, 2025

After a long quiet period they've laid foundations for Building 2 and the substation.

Oct 1, 2025

Building 2 looks externally complete

Mar 1, 2026

The cooling towers for Buildings 2 and 3 are both a little less than half done and the buildings still look like active construction sites.

Aug 19, 2026

Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. So we give it about 3 more months until it's operational. Building 3 appears to be slightly further than Building 2 was in March, so we estimate a 4-month lag.

Dec 1, 2026

Estimated operational date of Building 2.

Compute
383kH100-eq
IT Power
173MW
Cost
$6.6B
Mar 31, 2027

Estimated operational date of Building 3. Based on Building 3 construction looking about 4 months behind Building 2.

Compute
824kH100-eq
IT Power
345MW
Cost
$13.1B
Aug 28, 2027

Estimated operational date of Building 4. Based on Building 4 construction looking about 10 months behind Building 2.

Compute
1,400kH100-eq
IT Power
518MW
Cost
$19.6B
Jan 25, 2028

Estimated operational date of Building 5. Based on previous buildings being separated by about 5 months.

Compute
2,067kH100-eq
IT Power
690MW
Cost
$26.1B
Jun 23, 2028

Estimated operational date of Building 6. Based on previous buildings being separated by about 5 months.

Compute
2,941kH100-eq
IT Power
863MW
Cost
$32.7B

Sources

  1. Google's plans for wetlands in Fort Wayne
  2. Data center's diesel generators
  3. Project's history and tax abatement
  4. City Council approval

View our calculations for this data center, or read more about our methodology.