Claude, Texas, United States
Goodnight is an AI Data Center under construction, projected to host an estimated 2,011k H100-equivalent chips — supported by 1,006 MW — at a capital cost of $38.1 B. The timeline of IT power and compute capacity is based on satellite imagery, regulatory filings, structural similarity to known buildings, chip availability, and chip efficiency. Though named after the nearby locale of Goodnight, the data center is actually located in the town of Claude, Texas.
Satellite imagery
CURRENT COMPUTE
0 H100-eq
0 8-bit OP/s
PROJECTED
2,011k H100-eq
3.98e21 8-bit OP/s
CURRENT IT POWER
0 MW
PROJECTED IT POWER
1,006 MW
CURRENT COST
$0.0 B
PROJECTED COST
$38.1 B
Land clearing begins
Building 1 and 2 under construction.
Construction on Building 1 and 2 looks about halfway to completion. Foundations and utility trenches are visible for Building 3-4. Building 5-6 have an outline. The substation appears to be expanding.
Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. The substation expansion seems to be nearing completion.
Building 1 operational. This regulatory document lists the completion date for Building 1 as 2026-09-12, the current status suggests this estimate will not be met. From the timeline seen at the Abilene, Texas site for the same building styles we estimate operability to occur 8 months after the state seen in April 2026.
Building 2 operational. The completion date for Building 2 Tenant Improvement is 2026-11-07, about 2 months later than Building 1. We therefore add 2 months to the Building 1 operational date.
6 buildings are operational. This is based on:
Read more about our methodology.