Goodnight

Claude, Texas, United States

Goodnight is an AI data center under construction with AI chips owned by Google (speculative) and used by Google DeepMind (speculative). In Q4 2027, we project it to host an estimated 2,011k H100-equivalents of compute, supported by 1,006 MW of IT power at a capital cost of $38.1 B.

The timeline of IT power and compute capacity is based on satellite imagery, regulatory filings, structural similarity to known buildings, chip availability, and chip efficiency.

Though named after the nearby locale of Goodnight, the data center is actually located in the town of Claude, Texas.

OWNER Google STATUS Under construction USER Google DeepMind
Show compute as
Satellite view of Goodnight

Satellite imagery

Latest: Apr. 18, 2026 · 3 high-res images
View satellite explorer →

Scale & specifications

CURRENT COMPUTE

0 H100-eq

0 8-bit OP/s

PROJECTED

2,011k H100-eq

3.98e21 8-bit OP/s

CURRENT IT POWER

0 MW

PROJECTED IT POWER

1,006 MW

CURRENT COST

$0.0 B

PROJECTED COST

$38.1 B

HardwareNvidia B300, Nvidia Rubin

CoolingUnknown

Buildout

May 19, 20250K H100e
May 19, 2025

Land clearing begins

Oct 16, 2025

Building 1 and 2 under construction.

Dec 23, 2025

Construction on Building 1 and 2 looks about halfway to completion. Foundations and utility trenches are visible for Building 3-4. Building 5-6 have an outline. The substation appears to be expanding.

Apr 16, 2026

Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. The substation expansion seems to be nearing completion.

Dec 15, 2026

Building 1 operational. This regulatory document lists the completion date for Building 1 as 2026-09-12, the current status suggests this estimate will not be met. From the timeline seen at the Abilene, Texas site for the same building styles we estimate operability to occur 8 months after the state seen in April 2026.

Compute
124kH100-eq
IT Power
103MW
Cost
$3.9B
Feb 15, 2027

Building 2 operational. The completion date for Building 2 Tenant Improvement is 2026-11-07, about 2 months later than Building 1. We therefore add 2 months to the Building 1 operational date.

Compute
249kH100-eq
IT Power
206MW
Cost
$7.8B
Oct 1, 2027

6 buildings are operational. This is based on:

  1. A regulatory filing for Building 6 with a completion date of 2027-07-30. Normally there is a follow-up filing for "tenant improvement" which involves building the interior, with a completion date 1-3 months after the initial filing.
  2. A project deadline of EOY 2027 in the original tax abatement agreement
  3. The similar 8-building project in Abilene taking an estimated 2 years and 2 months.
Compute
2,011kH100-eq
IT Power
1,006MW
Cost
$38.1B

Sources

  1. Amended tax abatement agreement, with updated blueprints on p.46
  2. Original tax abatement agreement, with original blueprints and specs on the last page
  3. TABS database, with "Llano" data centers in the city of Claude
  4. Press release reports Google investing in a new data center in Armstrong County
  5. Clean Air Act Initial Prevention of Significant Deterioration permit application.