Vantage TX1San Antonio, Texas, United States
Full details →

CONSTRUCTION STATUS
Feb 15, 2026

Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the completion date reported on TDLR, based on the appearance, we believe it is operational. Reported IT power of 32 MW. Source

Compute
39kH100-eq
IT Power
32MW
Cost
$1.2B
Building
Substation
On-site power
Backup power
Cooling