202720262025202420232022
Start Campus Sines Data CampusSines, Setúbal, Portugal
OWNERNscale
USERMicrosoft
Full details →

CONSTRUCTION STATUS
Aug 16, 2026

Satellite imagery shows two black outlines, suggesting two buildings going up on a second adjacent site. There is an outline of another building as well. Further to the east, there is land clearing.

Compute
32kH100-eq
IT Power
33MW
Cost
$1.3B
Building
Substation
On-site power
Backup power
Cooling