QTS Richmond 3Sandston, Virginia, United States
Full details →

CONSTRUCTION STATUS
Feb 13, 2026

Building 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the perimeter and no cars in the carpark, but we expect they will be operational within 3 months. Building 4 has complete chillers and backup generators, while Building 5 has chillers but only a few backup generators - roughly the state of Building 1 on 2025-02-04.

Compute
58kH100-eq
IT Power
48MW
Cost
$1.8B