Microsoft-Nebius New JerseyVineland, New Jersey, United States
OWNERNebius
USERMicrosoft
Full details →

CONSTRUCTION STATUS
Jul 12, 2026

Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.

Compute
57kH100-eq
IT Power
50MW
Cost
$1.9B
Building
Substation
On-site power
Backup power
Cooling