2028202620252024
Meta Los LunasLos Lunas, New Mexico, United States
OWNERMeta
USERMeta
Full details →

CONSTRUCTION STATUS
Jul 28, 2026

Building 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months (it's been 10 months for this building). North-west of Building 1, the outline of a building of similar dimensions and style to Meta Jeffersonville's Building 1 is visible, this is labeled as Building 3. West of Building 1 we see more land clearing for what could be a building similar to Meta Jeffersonville's Building 2.

Compute
100kH100e
IT Power
87MW
Cost
$3.3B
Building
Substation
On-site power
Backup power
Cooling