Google MesaUnited States
OWNERGoogle
Full details →

CONSTRUCTION STATUS
May 15, 2026

Building 2 is close to being operational. There is only construction left on the backup generators, which are almost complete. Some equipment is also strewn around the building, especially near the air-cooled chillers. Preparation seems to have begun for Building 3 at the site.

Compute
126kH100-eq
IT Power
90MW
Cost
$3.4B
Building
Substation
On-site power
Backup power
Cooling