Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.
Compute
332kH100-eq
IT Power
303MW
Cost
$11.5B
Building
Substation
On-site power
Backup power
Cooling
Google Columbus - Satellite Explorer | AI Data Centers
See how satellite imagery, permits, and public disclosures are used to estimate the power capacity and performance of the Google Columbus data center.