Google ColumbusColumbus, Ohio, United States
OWNERGoogle
USERGoogle DeepMind
Full details →

CONSTRUCTION STATUS
Aug 5, 2026

Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.

Compute
332kH100-eq
IT Power
303MW
Cost
$11.5B
Building
Substation
On-site power
Backup power
Cooling