CONSTRUCTION STATUS
Apr 25, 2026

Building 1 perimeter is now fully paved. No other significant changes to Building 1 since the July 2025 image.

Compute
51kH100-eq
IT Power
42MW
Cost
$1.6B
Building
Substation
On-site power
Backup power
Cooling