CoreWeave NorwayØvrebø, Agder, Norway
OWNERCoreWeave
USEROpenAI
Full details →

CONSTRUCTION STATUS
Aug 15, 2026

Building 1 still operational. No new major developments since the April image, though the large land clearing to the southwest is now much more clearly visible. Bulk is saying this expansion could include AI datacenters, but we don't have any confirmation this expansion is for CoreWeave yet.

Compute
51kH100e
IT Power
42MW
Cost
$1.6B
Building
Substation
On-site power
Backup power
Cooling