According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.
Compute
93kH100-eq
IT Power
68MW
Cost
$2.6B
Building
Substation
On-site power
Backup power
Cooling
CoreWeave Ellendale ND - Satellite Explorer | AI Data Centers
See how satellite imagery, permits, and public disclosures are used to estimate the power capacity and performance of the CoreWeave Ellendale ND data center.