AWS New AlbanyNew Albany, Ohio, United States
OWNERAmazon
Full details →

CONSTRUCTION STATUS
May 18, 2026

Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.

Compute
201kH100-eq
IT Power
213MW
Cost
$8.1B
Building
Substation
On-site power
Backup power
Cooling