May 11, 2026

Building 1's cooling capacity increased to 53 air-cooled chillers (20 fans each), up from 30 in Oct 2025. This is more than enough for the announced 18,400 GB300 GPUs, but construction does not quite look complete, so we expect another 3 months until it's operational.