Microsoft Fairwater WisconsinMount Pleasant, Wisconsin, United States
OWNERMicrosoft
USEROpenAI
Full details →

CONSTRUCTION STATUS
May 15, 2026

The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new 9-building design, making way for Buildings 3-11. Work continues on the northern substation in Area 2.

Compute
446kH100-eq
IT Power
369MW
Cost
$14.0B
Building
Grid power
On-site power
Backup power
Cooling