202620252024
Google Pryor (North)Pryor, Oklahoma, United States
OWNERGoogle
USERGoogle DeepMind
Full details →

CONSTRUCTION STATUS
May 26, 2026

Building 2 looks almost complete, but still appears to have three cooling towers missing. We therefore expect another 3 months until full operation.

Compute
26kH100-eq
IT Power
53MW
Cost
$2.0B
Building
Substation
On-site power
Backup power
Cooling