Google LincolnLincoln, Nebraska, United States
OWNERGoogle
Full details →

CONSTRUCTION STATUS
May 12, 2026

Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete.

Compute
288kH100-eq
IT Power
141MW
Cost
$5.3B
Building
Substation
On-site power
Backup power
Cooling