At this point, Building 1 and 2 have since already been operational. Additionally, there is visible steam showing clear evidence of operational for both before this date.
Compute
87kH100-eq
IT Power
137MW
Cost
$5.2B
Building
Grid power
On-site power
Backup power
Cooling
Google Lancaster - Satellite Explorer | AI Data Centers