Google Council Bluffs (East)Council Bluffs, Iowa, United States
OWNERGoogle
USERGoogle DeepMind
Full details →

CONSTRUCTION STATUS
Jan 11, 2026

Building 3 has all 34 backup generators installed and 4 cooling towers installed, with 3 more cooling towers under construction. There are gaps between cooling towers suggesting that more could be added. Buildings 1 and 2 are running close to full capacity, given that water vapor is coming out of 5 of 7 cooling towers for each building. The land cleared in the southwest appears to be shaped for two more similar buildings, with notches for substations.

Compute
92kH100-eq
IT Power
158MW
Cost
$6.0B
Building
Grid power
On-site power
Backup power
Cooling