All air-cooled chillers have been disconnected and/or removed from the site, leaving only the cooling towers for cooling. The third substation looks complete, with red cables connected to the building.
Compute
276kH100-eq
Power
425MW
Cost
$12.9B
Building
Grid power
On-site power
Backup power
Cooling
Colossus 1 - Satellite Explorer | AI Data Centers