2027202620252024202320222021
AWS BerwickBerwick, Pennsylvania, United States
OWNERAmazon
USERAnthropic
Full details →

CONSTRUCTION STATUS
May 5, 2026

Buildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several additional building shells and pads are still in construction, but none are assumed operational due to all the construction work visible. This is based on satellite imagery from this date.

Compute
58kH100-eq
IT Power
77MW
Cost
$2.9B
Building
Substation
On-site power
Backup power
Cooling